Replacement of Cold Water Storage Tanks at Baddow Hall Junior School

Scope of Works:

Replacement of Cold Water Storage Tanks located on the school roof.

This project involved the removal of asbestos under controlled conditions - followed by the draining down of the cold water system and removal of the existing cold water tanks from the roof.

The new installation was for 2 Sarena GRP pre insulated tanks on new bases with all associated pipework, insulated and tested. Frost protection heaters and new lighting were also fitted and a new access doorway fitted into the water tank housing to assist with future maintenance. The tanks were chlorinated and a new Water Risk Assessment carried out. Specialised lifting equipment was used to remove the old tanks and lift new ones into position on the school roof - all work carried out within a secure perimeter.

Balm & Davies has extensive experience of working on sensitive sites with the care and professionalism required to complete any works with the least disruption to those present.

Baddow Hall Boiler

Baddow Hall Boiler

Baddow Hall Boiler